PROJECT DESCRIPTION
The project involves the design, construction, maintenance, and operation of a 100 MW greenfield grid-connected solar PV plant to be built in Pasuruan Regency, East Java. The transmission line for the plant is connected to Gondangwetan 150 kilovolt substation. The distance to the nearest switchyard would be approximately 4.3 kilometers from the project site.
ADDITIONAL INFORMATION
Project is "proposed" and full details are not available yet. For more information https//www.adb.org/projects/59099-001/main